Project Description

As originally proposed, this project consisted of three parts: improvements to Upper Hunt Camp Trail, improvements to Lower Hunt Camp Trail, and a connector trail. The project was identified as a priority project in the 2015 road and trail designation process.

A section of Upper Hunt Camp, formerly a narrow and unimproved ridgetop trail, was re-routed and the grade improved to create a more stable and sustainable trail. The highly erosive portions of trail were decommissioned. Drainage improvements were also implemented to alleviate chronically wet conditions and reduce erosion.

There is currently no timeline for the Lower Hunt Camp part of the project. 

Timeline

  • 2015: Project Identified
  • 2016–2017: Project Planning
  • April 13–May 15, 2017: MCOSD Administrative Public Comment
  • May/June 2017: CEQA Review
  • June 2017: Project Determination
  • 2018: Implementation on Upper Hunt Camp
  • Fall 2018: Work complete on Upper Hunt Camp